Building a Better Bridge

How a major investment in the Lamar DC Tie and a new SPP study could help unlock the value between East and West

For years, the DC ties between the Eastern and Western Interconnections have done a crucial job without attracting much attention. They are the bridges between two mammoth energy systems, carrying electrons over the invisible boundary that divides the American electric grid, hampered only by their limited transfer capability. However, a major federal investment is creating new momentum for East-West connectivity just as SPP prepares to explore how much additional value stronger connections between the two interconnections could deliver.

The Colorado Energy Office and Xcel Energy were recently selected for a $250 million U.S. Department of Energy award to modernize a key transmission connection between southeastern Colorado and Texas, advancing an idea at the heart of SPP’s new Western and Eastern Interconnection Capacity Expansion High-Priority Study (WE EXPAND) and potentially tripling the tie’s transfer capability. This investment marks a pivotal moment for grid reliability in the region by directly supporting this critical connection between the Western and Eastern Interconnections, aligning with SPP’s vision for a more connected, efficient and robust electric grid.
The Colorado-to-Texas Western-Eastern Intertie Modernization Initiative, or CO2TX, will modernize the existing Lamar DC tie and connect it to the higher-capacity May Valley substation, which ties directly to Xcel Energy’s Colorado Power Pathway transmission network. The project will also upgrade existing infrastructure rather than creating an entirely new transmission corridor, with a focus on replacing aging equipment and adding higher-capacity conductors.

“Reliability is at the heart of this project and everything we do at Xcel Energy,” said Robert S. Kenney, President, Xcel Energy-Colorado. “Modernizing the Lamar Tie will strengthen the connection between the Western and Eastern electric grids, helping us better serve customers during extreme weather, meet growing energy needs and make the most of affordable energy resources across the region. With support from the Department of Energy, this smart, cost-effective investment will strengthen reliability and deliver long-term value for customers and communities today and into the future.”
The project is expected to increase transfer capability between the two interconnections from approximately 210 megawatts to 700 MW. Future upgrades could expand that capability to as much as 2,000 MW as electricity demand grows. By strengthening this DC tie, SPP and its stakeholders will unlock new opportunities for resource sharing and cost savings, benefiting millions of customers across Colorado, Texas and New Mexico.
WE EXPAND
Just weeks before the CO2TX funding announcement, SPP's Board of Directors approved a new high-priority study focused squarely on opportunities like the Lamar DC tie improvements. The Western and Eastern Interconnection Capacity Expansion High-Priority Study (WE EXPAND) will examine ways to increase transfer capability between the two major interconnections and determine where greater connectivity can deliver value through strengthened reliability and resilience while lowering wholesale energy costs. SPP plans to work with stakeholders through the remainder of 2026 to define the scope and perform the study in 2027.
The timing makes the Lamar Tie investment especially significant. CO2TX does not replace the need for WE EXPAND. Instead, it illustrates the kind of opportunity the study is designed to examine on a broader scale. One connection moving from 210 MW to 700 MW is meaningful. However, WE EXPAND asks a bigger question: what could be possible if we strategically expanded East-West transfer capability across the wider system?
Increasing transfer limits between the Eastern and Western Interconnections by more than 5,500 MW could potentially produce hundreds of millions of dollars in annual savings, according to SPP's initial analysis. The DOE's draft 2026 National Transmission Needs Study also identified cross-interconnection expansion as an area with significant potential transmission value. SPP cited the study when announcing WE EXPAND, noting average price differences of $18-$33/MWh between the Western Interconnection and SPP's Eastern footprint.
Those price differences represent an opportunity: when lower-cost electricity is available in one interconnection but insufficient transmission capacity prevents it from reaching customers in the other, potential economic value can be left on the table. Greater connectivity can help change that.
SPP's transmission studies have repeatedly demonstrated that well-planned grid investments can produce benefits over their operating lives that exceed their costs. The Colorado–Texas modernization project is a real-world step toward achieving those outcomes. It reinforces the value of SPP’s leadership in planning, seams strategy and interconnection operations. As the nation’s only grid operator with a footprint spanning both interconnections, SPP is uniquely positioned to help maximize the benefits of this historic investment.
As WE EXPAND moves forward, SPP and its stakeholders will examine where additional transfer capability can create the greatest value for the region and what it would take to realize those opportunities. The study will help inform future conversations about transmission planning, investment and cost allocation.
While there is still considerable work ahead, the Lamar Tie improvements offer a glimpse of what a more connected future – by building a better bridge – could look like with increased opportunities to share resources creating a grid better positioned to serve growing electricity needs.